Scheduled | Actual | |
---|---|---|
Determination: | 02/02/2024 | 02/02/2024 |
Risk Level: | 02/02/2024 | 02/02/2024 |
Initial Market Research: | 03/21/2024 | 03/21/2024 |
Develop Solicitation Sourcing Team: | 03/25/2024 | 03/28/2024 |
Strategic Planning: | 06/11/2024 | 06/13/2024 |
Solicitation Drafting: | 07/26/2024 | 07/31/2024 |
Solicitation Posting: | 07/27/2024 | 08/07/2024 |
Bid Posting Length: (In days) | 35 | 45 |
Pre-bid Conference Date: | 08/13/2024 | 08/21/2024 |
Q&A Period: | 08/21/2024 | 09/11/2024 |
Bid Due Date: | 08/31/2024 | 09/14/2024 |
Evaluation: | 10/15/2024 | 10/31/2024 |
ASB Announced: | 10/16/2024 | |
Debrief Period Ends: | 10/24/2024 | |
Protest Period Ends: | 10/31/2024 | |
Protest Response Period Ends: | 11/14/2024 | |
Contract Award Date: | 11/15/2024 | |
Contract Completion Date: | 11/29/2024 |