| Scheduled | Actual | |
|---|---|---|
| Determination: | 05/30/2021 | 11/02/2021 |
| Risk Level: | 06/06/2021 | 11/04/2021 |
| Initial Market Research: | 07/06/2021 | 11/06/2021 |
| Develop Solicitation Sourcing Team: | 07/27/2021 | 02/16/2022 |
| Strategic Planning: | 09/25/2021 | 04/01/2022 |
| Solicitation Drafting: | 11/24/2021 | 06/14/2022 |
| Solicitation Posting: | 04/28/2025 | 04/28/2025 |
| Bid Posting Length: (In days) | 30 | 30 |
| Pre-bid Conference Date: | 05/06/2025 | 05/06/2025 |
| Q&A Period: | 05/14/2025 | 05/20/2025 |
| Bid Due Date: | 06/10/2025 | 06/10/2025 |
| Evaluation: | 07/20/2025 | 07/20/2025 |
| ASB Announced: | 07/21/2025 | 07/21/2025 |
| Debrief Period Ends: | 07/24/2025 | 07/24/2025 |
| Protest Period Ends: | 07/31/2025 | 07/30/2025 |
| Protest Response Period Ends: | 08/10/2025 | 07/30/2025 |
| Contract Award Date: | 08/15/2025 | 08/15/2025 |
| Contract Completion Date: | 09/01/2025 | 08/29/2025 |