Scheduled | Actual | |
---|---|---|
Determination: | 05/30/2021 | 11/04/2021 |
Risk Level: | 06/06/2021 | 12/24/2021 |
Initial Market Research: | 07/06/2021 | 11/02/2021 |
Develop Solicitation Sourcing Team: | 07/27/2021 | 02/16/2022 |
Strategic Planning: | 09/25/2021 | 04/01/2022 |
Solicitation Drafting: | 11/24/2021 | 06/14/2022 |
Solicitation Posting: | 04/28/2025 | 04/28/2025 |
Bid Posting Length: (In days) | 30 | 30 |
Pre-bid Conference Date: | 05/06/2025 | 05/06/2025 |
Q&A Period: | 05/14/2025 | |
Bid Due Date: | 06/10/2025 | |
Evaluation: | 07/14/2025 | |
ASB Announced: | 07/15/2025 | |
Debrief Period Ends: | 07/18/2025 | |
Protest Period Ends: | 07/25/2025 | |
Protest Response Period Ends: | 08/06/2025 | |
Contract Award Date: | 08/15/2025 | |
Contract Completion Date: | 09/01/2025 |