Contract Schedule For Contract #: 11121

Scheduled Actual
Determination: 05/30/2021 11/04/2021
Risk Level: 06/06/2021 12/24/2021
Initial Market Research: 07/06/2021 11/02/2021
Develop Solicitation Sourcing Team: 07/27/2021 02/16/2022
Strategic Planning: 09/25/2021 04/01/2022
Solicitation Drafting: 11/24/2021 06/14/2022
Solicitation Posting: 04/28/2025 04/28/2025
Bid Posting Length: (In days) 30 30
Pre-bid Conference Date: 05/06/2025 05/06/2025
Q&A Period: 05/14/2025
Bid Due Date: 06/10/2025
Evaluation: 07/14/2025
ASB Announced: 07/15/2025
Debrief Period Ends: 07/18/2025
Protest Period Ends: 07/25/2025
Protest Response Period Ends: 08/06/2025
Contract Award Date: 08/15/2025
Contract Completion Date: 09/01/2025