Contract Schedule For Contract #: 11121
|
Scheduled |
Actual |
Determination: |
05/30/2021 |
11/02/2021 |
Risk Level: |
06/06/2021 |
11/04/2021 |
Initial Market Research: |
07/06/2021 |
11/06/2021 |
Develop Solicitation Sourcing Team: |
07/27/2021 |
02/16/2022 |
Strategic Planning: |
09/25/2021 |
04/01/2022 |
Solicitation Drafting: |
11/24/2021 |
06/14/2022 |
Solicitation Posting: |
04/28/2025 |
04/28/2025 |
Bid Posting Length: (In days) |
30 |
30 |
Pre-bid Conference Date: |
05/06/2025 |
05/06/2025 |
Q&A Period: |
05/14/2025 |
05/20/2025 |
Bid Due Date: |
06/10/2025 |
06/10/2025 |
Evaluation: |
07/20/2025 |
07/20/2025 |
ASB Announced: |
07/21/2025 |
07/21/2025 |
Debrief Period Ends: |
07/24/2025 |
07/24/2025 |
Protest Period Ends: |
07/31/2025 |
|
Protest Response Period Ends: |
08/10/2025 |
|
Contract Award Date: |
|
|
Contract Completion Date: |
|
|
Currently there are no sales reports from the vendors on this contract.